Glossary · standstill period

Standstill period in public procurement

The standstill period is the time after the award decision during which the contracting authority may not yet sign the contract. In Norwegian it is karensperiode, in Finnish odotusaika, in German Stillhaltefrist or Wartefrist. It is a short window in which a losing bidder can challenge the result before the contract exists.

Updated · By Jurgis Mickevičius, Data Innovations

The EU rule: at least 10 days

At EU level the standstill period is set by the Remedies Directive 89/665/EEC (Article 2a), as amended by Directive 2007/66/EC. For contracts above the EU thresholds, the contract may not be concluded until at least 10 calendar days have passed, counted from the day after the award decision is sent by electronic means or fax. If other means are used, the period is longer: 15 days from sending or 10 days from receipt.

The directive also sets what the notice must contain. Each bidder concerned must receive the decision together with a summary of the relevant reasons and a precise statement of the standstill period. Countries may set a longer period, not a shorter one. If a contract is signed before the period ends, a court can declare it ineffective.

Norway, Finland, Germany and Lithuania

CountryLocal termMinimum lengthLegal basis
Norwaykarensperiode10 days (15 if the buyer does not use electronic communication)anskaffelsesforskriften § 25-2
Finlandodotusaika14 days from receipt of the decisionAct 1397/2016
GermanyWartefrist15 calendar days, 10 if sent electronically or by faxGWB § 134
Lithuaniaatidėjimo terminas10 days, 5 working days in simplified procurement (15 days if the notice was not sent electronically)Law on Public Procurement, Art. 86

Norway. Above the EEA thresholds the buyer notifies all bidders in writing and at the same time which supplier it has chosen, with reasons and the date the standstill period ends. The period runs from the day after the notice is sent. For national procurements (Part II) the buyer sets a "reasonable" period itself, and the rules give no fixed number of days. Disputes can go to the advisory complaints board KOFA. More: public tenders in Norway.

Finland. Above the EU thresholds, and for social, health and other specific services and concessions, the contract may be signed at the earliest 14 days after the bidder received the decision and the appeal instructions. In some call-offs under framework agreements and dynamic purchasing systems the period is shorter, 10 days. The odotusaika does not apply to national procurements or direct awards. More: public tenders in Finland.

Germany. Under § 134 GWB the buyer informs unsuccessful bidders in text form of the winner's name, the reasons for rejection and the earliest date the contract can be concluded. The period starts the day after sending; the date of receipt does not matter. Since the Vergabebeschleunigungsgesetz took effect on 1 July 2026, the duty no longer applies to awards under framework agreements and dynamic purchasing systems. More: public tenders in Germany.

Lithuania. Article 86(8) of the Law on Public Procurement says the contract must be signed without delay, but not before the standstill period ends. The standstill does not apply to low-value procurements, although the review rules still do.

When there is no standstill period

The exceptions look similar across countries because they come from the same directive. Most often there is no standstill period when:

  • only one bidder took part and the contract goes to that bidder;
  • the contract is a call-off under an existing framework agreement or dynamic purchasing system (in Finland a shorter period applies in some cases);
  • the contract did not have to be advertised, for example because of extreme urgency.

Lithuania also exempts contracts concluded orally. If framework agreements are your main channel, be aware that you often will not have a chance to challenge individual call-offs before they are signed.

What a losing bidder can do

The standstill period is short, so act at once. The usual sequence:

  1. Read the notice the same day. Check when it was sent, when the period ends and which reasons are given.
  2. Ask for an explanation. Ask how your tender and the winner's were scored against each criterion. Many buyers answer quickly, and that is often enough to see whether a challenge makes sense.
  3. Complain to the buyer. In Lithuania a claim to the buyer is a required step before going to court. In Germany the breach must be raised with the buyer promptly (Rüge). In Finland you can ask the buyer to correct its decision (hankintaoikaisu).
  4. Go to the review body or court. In Norway that is KOFA or the courts, in Finland the Market Court (markkinaoikeus), in Germany the public procurement tribunal (Vergabekammer), in Lithuania the regional court.

Deadlines for complaints do not always match the standstill period, and in some countries they run from receipt of the notice, not from sending. The notice itself states the dates, so read it first. In high-value disputes it is worth talking to a lawyer who knows the local practice.

How to use award decision letters

Even if you do not plan to challenge anything, the award notice is useful information. It gives you the winner's name, often the price and the quality scores. Keep a simple table: buyer, winner, price, your score and the winner's score. After a few tenders you will see where you keep losing points and which competitors win on price and which on quality.

Once the contract is signed, the buyer publishes a contract award notice. It is public and appears in TED, Doffin or Hilma, so you can also follow tenders you did not bid for. On large contracts the winner often looks for subcontractors and suppliers, which makes the award notice a sales lead as well.

MarketScope collects notices from TED, Doffin, Hilma and oeffentlichevergabe.de automatically, including contract award notices, and marks market consultations and prior information notices as early signals.

Frequently asked questions

What is a standstill period?

It is the period after the award decision during which the contracting authority may not sign the contract. Losing bidders can use it to challenge the decision.

How long is the standstill period in the EU?

Under Remedies Directive 89/665/EEC, for contracts above the EU thresholds it is at least 10 calendar days when the decision is sent electronically or by fax, and longer otherwise. Countries may set a longer period.

How long is the standstill period in Norway and Finland?

In Norway the karensperiode above the EEA thresholds is at least 10 days. In Finland the odotusaika is 14 days from receipt of the decision, and it does not apply to national procurements.

When is there no standstill period?

Typically when only one bidder took part, when the contract is a call-off under a framework agreement or dynamic purchasing system, or when the contract did not have to be advertised.

What should I do if I lose a tender?

Read the notice at once, ask the buyer to explain the scoring, complain to the buyer if needed and only then go to the review body or court. Deadlines are short and the notice states the exact dates.