What is a framework agreement? How it works and how to get on one
A framework agreement (Lithuanian preliminarioji sutartis, Norwegian rammeavtale, Finnish puitejärjestely, German Rahmenvereinbarung) sets the terms under which a buyer will order goods, services or works over several years. Win one tender and orders can keep coming for a long time; lose it and you usually cannot join until the next tender. This page explains how these agreements work in the EU, Lithuania, Norway, Finland and Germany.
What a framework agreement is
Framework agreements are governed by Article 33 of Directive 2014/24/EU. A framework agreement is an arrangement between one or more buyers and one or more suppliers that sets the terms of future orders: prices or how they are calculated, quantities or their limits, delivery times. The framework itself is not yet an order. Individual contracts are awarded later, when the buyer needs something.
Under the directive a framework agreement may not last longer than four years, except in exceptional, duly justified cases, in particular relating to its subject. It can be used only by the buyers clearly identified in the procurement documents, and only with the suppliers that were party to it from the start. Orders may not substantially change its terms. A short definition is also in the procurement glossary.
For a supplier it matters that the value shown in the notice is usually the estimated maximum value of all orders over the whole term. Whether the buyer commits to any minimum volume is stated in the draft contract. Often there is no such commitment.
How orders are allocated
With one supplier
Orders are awarded on the terms of the framework agreement. The buyer may ask the supplier in writing to complete its offer, for example with a specific quantity or delivery date, but the terms cannot be changed substantially.
With several suppliers
- Without reopening competition. If the agreement sets all terms and objective rules for choosing the supplier for each order, orders follow those rules. That can be a rotation, a ranking from the tender result or another method described in advance.
- Reopening competition. If not all terms are set, the buyer invites the parties to submit offers for a specific order. This is the so-called mini-competition: the deadline is short, and the supplier with the best offer under the criteria stated in advance wins.
- A mix of both. Some orders go directly and others through a mini-competition, if the documents provide for it.
In practice, getting onto a multi-supplier framework does not guarantee any orders. In mini-competitions you compete again on price and quality, so it pays to know in advance how offers will be evaluated.
How to spot one in notices
TED notices under eForms state that the procurement involves a framework agreement, often with the maximum number of suppliers. In Doffin look for the word rammeavtale, in Hilma puitejärjestely, in German notices Rahmenvereinbarung or Rahmenvertrag.
The most useful information is in the contract award notice. It tells you who won and when the agreement was concluded. Add the term and you get the date by which the buyer will have to run a new tender. Sometimes a prior information notice or a market consultation announces it in advance.
Lithuania, Norway, Finland and Germany
Lithuania
The Lithuanian Public Procurement Law also limits a framework agreement to four years, except in justified cases related to the subject that are stated in the notice. Tenders run in CVP IS. Some framework agreements are concluded by the central purchasing body CPO LT and then used by other institutions. More: public tenders.
Norway
In Norwegian it is rammeavtale. Under section 26-1 of the procurement regulation (anskaffelsesforskriften) the term generally may not exceed four years unless special circumstances apply. With several suppliers, the buyer either sets an allocation key (fordelingsnøkkel) or holds a new competition between the suppliers, usually called a minikonkurranse. Norwegian buyers use rammeavtale often, so one won tender can bring orders for several years. More: public tenders in Norway.
Finland
In Finnish it is puitejärjestely, and the reopened competition is called kevennetty kilpailutus. The same EU rules apply. The central purchasing body Hansel also concludes framework agreements for state bodies, so some large agreements serve several organisations at once.
Germany
In German it is Rahmenvereinbarung. Under section 21 of the Vergabeverordnung (VgV) the term is at most four years, except in justified cases. If not all terms are set, orders are awarded through a new competition between the parties: the buyer contacts the suppliers in text form, sets an adequate deadline and chooses the most economically advantageous offer.
Framework agreement vs contract, and central frameworks
Framework agreement vs contract. A public contract is an order: the buyer commits to buy a defined scope at a defined price. A framework agreement only fixes the terms of future orders. The orders themselves are separate contracts, usually called call-offs, awarded under the framework when the need arises. That is why a framework can be worth millions on paper and still bring a supplier few orders.
Single-supplier and multi-supplier frameworks. With one supplier, call-offs go straight to it on the agreed terms. With several, the buyer either follows a ranking or rotation set in advance or runs a mini-competition among the suppliers on the framework.
Central framework agreements. A central purchasing body can conclude a framework on behalf of many buyers, such as ministries, municipalities or hospitals. Those buyers then place call-offs without running their own tender. Examples are CPO in Lithuania, DFØ in Norway and Hansel in Finland. For a supplier this means one tender decides access to a large group of buyers for up to four years.
Framework service agreement. The term is also used in private B2B contracts for a master agreement that sets the terms of later service orders. The logic is the same, but the public procurement rules on duration, parties and mini-competitions do not apply.
Common mistakes
- Reading the value as a guaranteed order. The notice value is usually a ceiling, not a promise.
- Not tracking when the current agreement ends. The next tender comes only after several years, so it is easy to miss.
- Bidding too low just to get on. Prices apply for the whole term. Read the price indexation clauses.
- Not preparing for mini-competitions. Deadlines for orders are short, so pricing and documents need to be ready in advance.
- Ignoring lots. Large agreements are often split by region or product group, and a smaller company has a better chance of winning one lot.
Short checklist
- Check the term, any extension options and who may use the agreement.
- Find out whether it has one or several suppliers and how orders are allocated.
- Read whether there is a minimum volume and price indexation.
- See whether the tender is split into lots.
- Note the end dates of current agreements in your market.
MarketScope filters notices from TED, Doffin, Hilma and oeffentlichevergabe.de by CPV codes and keywords in several languages, so a new tender shows up in your list when it is published.
Related terms: CPV codes · prior information notice · standstill period · ESPD · dynamic purchasing system. All terms: public procurement glossary. Where to find framework tenders: public tenders in the EU and the Nordics · Norway · Germany · construction.
Frequently asked questions
What is a framework agreement?
It is an arrangement between one or more buyers and one or more suppliers that sets the terms of future orders. Individual contracts are awarded later, when the buyer needs something.
What is the difference between a framework agreement and a contract?
A framework agreement sets the terms (prices or how they are calculated, quantities, delivery) but is not yet an order. The actual contracts, called call-offs, are awarded under it later, when the buyer needs something.
How long can a framework agreement last?
Under Article 33 of Directive 2014/24/EU no longer than four years, except in exceptional, duly justified cases. The same limit applies in Lithuania, Norway and Germany.
What is a central framework agreement?
It is a framework agreement concluded by a central purchasing body on behalf of many buyers, for example ministries, municipalities or hospitals. Those buyers then place call-offs under it without running their own tender.
Can I join an existing framework agreement?
No. Only the suppliers that were party to it from the start can receive orders. The next chance comes with a new tender when the current agreement ends.
What is a mini-competition?
When a framework has several suppliers and not all terms are fixed, the buyer invites them to bid for a specific order. In Norway this is called minikonkurranse, in Finland kevennetty kilpailutus.
Does the value in the notice guarantee orders?
Usually not. The value is normally the estimated maximum of all orders over the whole term. Whether there is a minimum volume is stated in the draft contract.