Glossary · EU thresholds

EU public procurement thresholds 2026–2027

EU thresholds are the amounts, excluding VAT, from which a procurement falls under the EU directives: mandatory publication in TED, minimum deadlines, the ESPD and the remedies rules. Below you will find the 2026–2027 thresholds in euros, Norway's EEA thresholds in kroner, some national thresholds and the rules buyers use to estimate contract value.

Updated · By Jurgis Mickevičius, Data Innovations

EU thresholds 2026–2027

The thresholds are recalculated every two years in line with the WTO Government Procurement Agreement, so they move slightly with exchange rates. From 1 January 2026 to 31 December 2027 the amounts set by Commission Delegated Regulations (EU) 2025/2152 (general procurement under Directive 2014/24/EU), 2025/2150 (utilities under Directive 2014/25/EU) and 2025/2151 (concessions) apply. All amounts exclude VAT:

ProcurementThreshold (EUR excl. VAT)
Works (all contracting authorities and utilities)5,404,000
Supplies and services, central government authorities140,000
Supplies and services, sub-central authorities (municipalities, regions, hospitals)216,000
Supplies and services, utilities (energy, water, transport, postal)432,000
Social and other specific services (Annex XIV, Directive 2014/24/EU)750,000
Social and other specific services, utilities1,000,000
Concessions5,404,000

In 2024–2025 the works threshold was EUR 5,538,000, central government supplies and services EUR 143,000, sub-central EUR 221,000 and utilities EUR 443,000. The thresholds for social and specific services did not change, because they are not tied to the WTO agreement.

What changes above and below the threshold

Once the estimated value reaches the EU threshold, the procurement must be published in TED and the buyer must respect the minimum tender deadlines in the directive. For an open procedure that is 35 days from the date the notice is sent, and the buyer may cut 5 days if tenders are submitted electronically. If a prior information notice was published earlier, the deadline can be shorter still.

Above the threshold the buyer must accept the ESPD as preliminary evidence that a supplier meets the selection criteria. Certificates are normally requested from the winner only. After the award decision a standstill period starts, during which the contract cannot be signed, and a losing bidder can challenge the result under the Remedies Directive.

Below the threshold national rules apply. They tend to be more flexible: shorter deadlines, lighter documents and sometimes no standstill period at all. For a supplier the key point is that these tenders usually do not reach TED. You find them on national portals: Doffin in Norway, Hilma in Finland, and federal and state portals in Germany.

Norway's EEA thresholds in NOK

Norway applies the EU thresholds through the EEA Agreement and converts them into kroner. The new EEA thresholds took effect in Norway on 21 April 2026, later than in the EU. Amounts excluding VAT, from the overview published by the Norwegian Agency for Public and Financial Management (DFØ) on anskaffelser.no:

ProcurementPrevious (NOK)New (NOK)
Central government supplies and services1.49 million1.63 million
Other contracting authorities, including municipalities and counties: supplies and services2.3 million2.5 million
Works57.8 million62.9 million
Special, health and social services7.8 million8.7 million
Utilities (forsyningsforskriften): supplies and services4.6 million5 million
Utilities: special, health and social services10.4 million11.6 million

More on Doffin and bidding in Norway: public tenders in Norway.

National thresholds: Norway, Finland, Lithuania

Norway. The national threshold is NOK 1.3 million excluding VAT. From that amount Part II of the procurement regulation (anskaffelsesforskriften) applies, so the contract has to be advertised on Doffin even when it is below the EEA threshold. This figure did not change in 2026.

Finland. Section 25 of the Act on Public Procurement and Concession Contracts (1397/2016) sets national thresholds of EUR 60,000 for supplies and services and EUR 150,000 for works. Social, health and other specific services and concessions have higher amounts. From the national threshold the contract is advertised on Hilma. More: public tenders in Finland.

Lithuania. The Law on Public Procurement separates international procurement (from the EU threshold), simplified procurement (below it) and low-value procurement with even lighter rules. The international threshold for social and other specific services is EUR 750,000, the same as in the directive. The low-value amounts have been amended several times, so check the current version on the legal register e-TAR or the Public Procurement Office website.

Germany. Above the EU thresholds the GWB and the VgV apply; below them the UVgO, VOB/A and state rules. More: public tenders in Germany.

How contract value is estimated

Whether a threshold is reached depends on the estimated value of the procurement, not on the final contract price. Article 5 of Directive 2014/24/EU sets the rules, and national laws follow them:

  • the value is the total amount payable excluding VAT, including options, renewals and any prizes or payments to participants;
  • it is assessed when the contract notice is sent or, where there is no notice, when the procedure starts;
  • for a framework agreement or a dynamic purchasing system, the value is all contracts expected over its whole term;
  • when the procurement is divided into lots, the value of all lots is added up.

A procurement may not be split to keep it below the threshold. The directive allows one exception: small lots (up to EUR 80,000 for supplies and services, up to EUR 1,000,000 for works) may be awarded under national rules as long as their combined value does not exceed 20% of the value of all lots. In Norway the lot limits from April 2026 are NOK 932,000 for supplies and services and NOK 11.6 million for works.

This has a practical side for suppliers. If you see several similar small tenders from the same buyer within a short time, it is worth asking whether the total reaches the EU threshold. Buyers take that question seriously, because improper splitting is a ground for a complaint.

What it means for suppliers

Thresholds tell you where to look. Large works or service tenders from several countries are easy to follow in TED. Municipal supply and service contracts between the national and the EU threshold often stay on the national portal only, and that is where competition tends to be thinner. If you only search TED, you never see them.

Thresholds also tell you what process to expect. Above the EU threshold you can plan around the directive's deadlines, use the ESPD and rely on a standstill period. Below it the rules differ from country to country, so read the tender documents with extra care.

MarketScope collects notices from TED, Doffin, Hilma and oeffentlichevergabe.de automatically, so you see both tenders above the EU thresholds and national ones. Market consultations and prior information notices are marked as early signals.

Frequently asked questions

What are the EU procurement thresholds for 2026?

For 2026–2027 the works threshold is EUR 5,404,000, central government supplies and services EUR 140,000, sub-central authorities EUR 216,000 and utilities supplies and services EUR 432,000. All amounts exclude VAT.

What changes when a contract is above the EU threshold?

It must be published in TED, the directive's minimum tender deadlines apply, the buyer must accept the ESPD, and a standstill period and the EU remedies rules apply after the award decision.

What are Norway's EEA thresholds?

From 21 April 2026 the threshold for central government supplies and services is NOK 1.63 million, for municipalities and other authorities NOK 2.5 million and for works NOK 62.9 million. The national threshold stays at NOK 1.3 million.

Are options included in the estimated contract value?

Yes. The estimated value is the total amount payable excluding VAT, including options and renewals. When a contract is divided into lots, the value of all lots is added up.

Can a buyer split a contract to stay below the threshold?

No, artificial splitting is not allowed. The only exception is small lots (up to EUR 80,000 for supplies and services, EUR 1 million for works) awarded under national rules, as long as they make up no more than 20% of the total value of all lots.

See what your market is doing this week